Overview
Gateway Plaza was a Negotiated GMP contract delivery between Rockwell Construction Co. and Lin Development Corp. in Chambersburg, Pennsylvania. The project consisted of 23,000 sq. ft. of shell retail space with future Tenant Fit-Out.
Project Data
Owner: Chambersburg Gateway Shopping Center
Floor Area: 23,000 sqft
Method of Award: Negotiated GMP
Construction Cost: $1.75 Million
Change Order Amount: $90,000.00 (Scope Additions)
Original Quoted Duration: 12 Months
Actual Duration: 14 Months (delay due to COVID Shutdown)