Overview

The new Mercersburg Academy Squash Center is a 12,300 square foot addition to the Nolde Athletic Center. The facility houses 10 squash courts and additional viewing areas for the Academy Squash Team. The Squash Court was completed in a seven month period through the spring and summer and was ready for play for the fall school year.

 

 

Project Data

Floor area:  12, 300 sq. ft.
Construction Cost: Original GMP $2.1 million
Method of Award: Negotiated General Contract
Change Order Amount: ($379,120.00) Scope Change Credit
Original Quoted Duration: 7 months
Actual Duration: 7 months

 

 

 